below 80% AMI ($89,400).
Total Project Costs = $2,659,500
# Of Units = 6
Total Development Cost Per Unit = $443,250
Impact Fund Award Total = $1,187,580
Grant Award Per Unit = $197,930
Example of possible funding scenarios (each unit will be unique based on
buyer):
Impact Fund Value Gap Subsidy Per Unit = $145,850
Impact Fund Affordability Gap Subsidy Per Unit = $51,080
Administration Fee Per Unit = $1000
Typical Grant Per Unit = $197,930
Typical Development Cost Per Unit =$443,250
Typical Grant Award Per Unit = $197,930
Average Price to Buyer = $245,320
The Housing Partnership is the grant recipient and will be leading the project.
Their tentative timeline includes:
Design & Bid - Spring/Summer 2025
Construction Start- Fall/Winter 2025
Construction Finish- Summer 2026
The Housing partnership is responsible for the construction and sale of all
homes. More details will be available as their project plan develops.
Attachments:
2.
Last Month:
·
·
·
·
·
·
Ansul system test and inspection
Kitchen equipment start up
Initial kitchen inspection completed
All flooring finishing by 1/31
Window shades complete
Framed, drywall, mud, and taped Bulk Heads (loading dock and corridor
RFI’s)
·
Patched, mud, and taped all damaged areas or touch up areas
throughout the building.
·
·
·
·
·
·
·
Drywall, mud, and sand pocket door
Walk in cooler and freezer start up.
Exhaust hood start up
Doors and hardware
Installed eye wash station in sick room
Labeling in the mechanical room
Relocated heater in the loading dock