Application and Certification for Payment No. 10 for $115,945.05 to Knutson Construction RE: Childcare Facility.
body
The January payment application includes but is not limited to vinyl flooring, carpet flooring, and walk off flooring installations. Electrical continued devicing out, installing remaining fixtures, fire alarm systems, and lighting control panels. This application also includes labor for miscellaneous specialty items, door hardware, finish carpentry work, as well as glazing and remaining fire sprinkler scopes. As of the date of this application, the project is 94.15 percent complete.
recommendation
City Administrator Recommendation: City Council Approve Application and Certification for Payment No. 10 for $115,945.05 to Knutson Construction RE: Childcare Facility.