Child Care Center Construction Update
body
MAY - Knutson continued with selective demolition throughout the space. The mechanical contractor continued with underground plumbing and finished up all the underground rough ins besides the kitchen areas. Electricians finished up their underground electrical work. All saw cuttings of the new wall openings were finished up and reinforced angle iron or lintels were installed above new openings. The masonry contractor was onsite cleaning and infilling all brick for these new openings. Metal fabricator drilled for all dowels at floor saw cutting areas, so dowel reinforcement can be installed prior to concrete pour back. Mechanical and electrical trades started on all above ceiling rough ins. This includes, but is not limited to new water lines, main air ducts, branch lines, and electrical runs. The exterior signage is being fabricated off site.
JUNE- This month we continued with misc. demolition throughout the building, exterior concrete, playground excavations, playground equipment install, above ceiling rough ins, underground plumbing, plumbing backfills, and we finished concrete pour back on the interior of the building and the kitchen area. We began structural steel this week and interior steel stud framing which will carry out for the following weeks. MEP in wall roughs will follow the stud walls, and eventually we’ll start with sheet rock in July. We received and turned in pricing for Proposal Request (PR) #1. The PR functions like a change order. The GMP contract has a contingency included that is paying for the changes, so we are moving funds from contingency to be allocated for the line items and the overall contract dollar amount remains unchanged. The majority of this change order addressed unforeseen conditions discovered within the existing building. These include the need for removal and replacement of clay tile and gypsum board insulation and vapor barriers in specific areas. Additionally, struct...
Click here for full text