Childcare Center Construction Update
body
Last Month:
• Ansul system test and inspection
• Kitchen equipment start up
• Initial kitchen inspection completed
• All flooring finishing by 1/31
• Window shades complete
• Framed, drywall, mud, and taped Bulk Heads (loading dock and corridor RFI’s)
• Patched, mud, and taped all damaged areas or touch up areas throughout the building.
• Drywall, mud, and sand pocket door
• Walk in cooler and freezer start up.
• Exhaust hood start up
• Doors and hardware
• Installed eye wash station in sick room
• Labeling in the mechanical room
• Relocated heater in the loading dock
• Installed carpet in offices and multi-purpose rooms
• Installed resilient athletic flooring in Activity Room
• Finished bathroom accessories
• Finished visual displays, grab bars, and other misc. div 10 items
• Electrical ceiling finishes
• Mounted lighting control boxes in Mechanical room
• Cleaning ongoing
This Month:
• Last of the glazing
• Continue with punch list corrections
• Continue with cleaning
• Final punch and walk through
• Final inspections
• Kitchen final
• Furniture / furniture punch list
• Lake Shore Equipment
• Other owner FFE
Kids Rock! has hired Director, Food Service Manager, and Assistant Director. There are 30+ applicants for Lead Teacher positions and 90+ applicants for Aide positions. Interviews will be set up for late February-early March. Furniture, Fixtures, and Equipment is arriving and rooms are filling up! Appliances are installed. There are 125+ kids on the pre-enrollment list. Families will be able to sign up for tours late February- early March and will be able to secure a spot with a down payment following their tour. Staff training, licensing inspection, and an Open House will take place in April with an anticipated opening date sometime in May.