File #: 2025-133    Version: 1
Type: Motion Status: Passed
File created: 4/17/2025 In control: City Council
On agenda: 4/22/2025 Final action: 4/22/2025
Title: Contract Change Order No. 13 for a Contract Increase of $11,182.36 to Knutson Construction RE: Childcare Facility.
Attachments: 1. Luverne-CO #13

title

Contract Change Order No. 13 for a Contract Increase of $11,182.36 to Knutson Construction RE: Childcare Facility.

 

body

This change order includes the following scope changes: additional return air grilles per punch list from mechanical contractor; additional foot pulls to garbage receptacles (per DHS requirements); and added a drop ceiling to storage room 138 per code requirements. These changes result in a net increase of $11,182.36, which will come out of the contingency balance. After this change order, the balance remaining in contingency is $181,006.78.  The guaranteed maximum price (GMP) remains unchanged.

 

recommendation

City Administrator Recommendation: City Council Approve Contract Change Order No. 13 for a Contract Increase of $11,182.36 to Knutson Construction RE: Childcare Facility.