Legislation Details

File #: 2024-325    Version: 1
Type: Motion Status: Passed
File created: 11/21/2024 In control: City Council
On agenda: 11/26/2024 Final action: 11/26/2024
Title: Application and Certification for Payment No. 7 for $1,003,367.30 to Knutson Construction RE: Childcare Facility.
Attachments: 1. 2440038 Luverne Childcare Center (Billing #07 - October 2024)

title

Application and Certification for Payment No. 7 for $1,003,367.30 to Knutson Construction RE: Childcare Facility.

 

body

This payment application is requested progress payment for October 2024. These activities include but are not limited to all casework and countertop materials and some casework installation throughout the space. We finished up the new aluminum storefront glazing systems and continued with working on the new hardware. Acoustical ceilings continued followed by electrical light fixtures, low voltage devices, grilles, registers, and diffusers. The kitchen had the protect-all flooring installed to be ready for kitchen equipment in November. Tiling continued in the bathrooms and plumbers followed with installing sinks & toilets. As of the date of this payment application, the project is 82.54 percent complete.

 

recommendation

City Administrator Recommendation: City Council Approve Application and Certification for Payment No. 7 for $1,003,367.30 to Knutson Construction RE: Childcare Facility.