Title: Change Order No. 15 for a Contract Increase of $23,190.91 to Knutson Construction RE: Childcare Facility.
Attachments: 1. Luverne Childcare - OCO #015 _Redacted

title

Change Order No. 15 for a Contract Increase of $23,190.91 to Knutson Construction RE: Childcare Facility.

 

body

This change order includes adding shelving to storage room 128 and replacing 11 door and window thermopane's with broken seals.  These changes result in a net increase of $23,190.91, which will come out of the contingency balance. After this change order, the balance remaining in contingency is $156,482.63.  The guaranteed maximum price remains unchanged.

 

recommendation

City Administrator Recommendation: City Council Approve Change Order No. 15 for a Contract Increase of $23,190.91 to Knutson Construction RE: Childcare Facility.