Legislation Details

File #: 2025-53    Version: 1
Type: LEDA Director's Report Informational Item Status: Passed
File created: 2/6/2025 In control: Economic Development Authority
On agenda: 2/10/2025 Final action: 2/10/2025
Title: Southwest MN Housing Partnership - Reisch Addition Twinhome Project
Attachments: 1. Reisch_Thomes_Plans_052924, 2. Impact Fund Income Limits 2024 (1)

title

Southwest MN Housing Partnership - Reisch Addition Twinhome Project

 

body

The Southwest Minnesota Housing Partnership (SWHP) will be awarded $1,187,580 Impact Fund Dollars from the MN Housing Board of Directors for their 2024 Single Family Housing application.  The funds will be used to construct twin homes in Luverne.

 

Proposed Project:

SMHP will construct three twin homes (6 units) on three lots in the Reisch Addition.  The units will be three-bedroom, two-bathroom, two-car garage, single-level twin homes with one shared wall.  

 

SMHP applied for state Impact Funds to bridge the VALUE GAP and AFFORDABILITY GAP.  The Value Gap addresses the difference in the cost it takes to build a project, and the dollar amount at which it can be appraised and sold.  The Affordability Gap addresses the gap between what a property is selling for and what the buyer can afford.   Value Gap will be used for the six units for households at or below 100% AMI (household income limit of $111,700).  Any Affordability Gap provided will be limited to households at or below 80% AMI ($89,400).

 

Total Project Costs = $2,659,500

# Of Units = 6

Total Development Cost Per Unit = $443,250

 

Impact Fund Award Total = $1,187,580

Grant Award Per Unit = $197,930

 

Example of possible funding scenarios (each unit will be unique based on buyer):

 

Impact Fund Value Gap Subsidy Per Unit = $145,850

Impact Fund Affordability Gap Subsidy Per Unit = $51,080

Administration Fee Per Unit = $1000

Typical Grant Per Unit = $197,930

 

Typical Development Cost Per Unit =$443,250

Typical Grant Award Per Unit = $197,930

Average Price to Buyer = $245,320

 

The Housing Partnership is the grant recipient and will be leading the project.  Their tentative timeline includes:
Design & Bid - Spring/Summer 2025

Construction Start- Fall/Winter 2025

Construction Finish- Summer 2026

The Housing partnership is responsible for the construction and sale of all homes.  More details will be available as their project plan develops.