Title
Change Order No. 6 for a Contract Increase of $29,628.00 to Henning Construction RE: Highway 75 Reconstruction Project
Body
Change Order No. 6 provides for the replacement of two valves and associated fittings at the water tower after field investigation identified corrosion in the existing components. The City water department determined it was beneficial to complete this work at this time while the highway project is underway to maintain a reliable and operational water system. The change order results in a net increase of $29,628, with work performed at existing contract unit prices and no impact to contract time.