Change Order No. 4 with No Net Change Amount and Change Order No. 5 for a Contract Increase of $23,000.00 to Henning Construction RE: Highway 75 Reconstruction Project
body
Change Order No. 4 for the TH 75 project approved a substitution of pipe bedding material from fine aggregate to ¾-inch washed rock, which was accepted by the City and engineer with no impact to cost or project timeline. Change Order No. 5 addressed exploratory digging to locate unknown utilities not identified in the original plans, with work directed by the engineer as needed. This change could result in a $23,000 increase to the contract, split between City and State funding, while maintaining the original project schedule if the contractor needs to use all hours of time for crew and exploratory digging.