Legislation Details

File #: 2025-377    Version: 1
Type: Motion Status: Passed
File created: 12/11/2025 In control: City Council
On agenda: 12/16/2025 Final action: 12/16/2025
Title: Change Order No. 16 for a Contract Increase of $65,352.76 to Knutson Construction RE: Childcare Facility.
Attachments: 1. Luverne-CO #16

Title

Change Order No. 16 for a Contract Increase of $65,352.76 to Knutson Construction RE: Childcare Facility.

 

Body

This change order is for replacing the existing sanitary sewer line back to the main; table, chairs and a lectern to facilitate staff training in the board room; and a monument sign to be fabricated and installed near Blue Mound Ave/Roundwind Road.

These changes result in a net increase of $65,352.76, which will come out of the contingency balance. After this change order, the balance remaining in contingency is $91,129.87. The GMP remains unchanged.