Change Order No. 6 for a Contract Decrease of $38,000 to Hoogendoorn Construction RE: Luverne Aquatics and Fitness Center Expansion and Remodel Project.
body
Upon Hoogendoorn's completion of punch list items for the Luverne Aquatics and Fitness Center Remodel project, the contract balance to close the project was $72,797.11. The City has assessed liquidated damages with this change order in the amount of $38,000. With the acceptance of this change order, the architect will process final paperwork and payment request in order to close this project out.
recommendation
City Administrator Recommendation: City Council Approve Change Order No. 6 for a Contract Decrease of $38,000 to Hoogendoorn Construction RE: Luverne Aquatics and Fitness Center Expansion and Remodel Project.