Contract Change Order No. 12 for a Contract Increase of $12,224.09 to Knutson Construction RE: Childcare Facility.
body
This change order includes the following scope changes: Lowered the bulkhead near employee entrance; Added bulkhead and ceiling scope in loading dock; Added miscellaneous brick patch work throughout; Changed door handles per RFI response; Added data drop for Watch Me Grow monitor; Changed (2) sets of grab bars in kids stalls because of flush valve conflicts.
These changes result in a net increase of $12,224.09, which will come out of the contingency balance. After this change order, the balance remaining in contingency is $192,189.14. The guaranteed maximum price remains unchanged.
recommendation
City Administrator Recommendation: City Council Approve Contract Change Order No. 12 for a Contract Increase of $12,224.09 to Knutson Construction RE: Childcare Facility.