Title: Kids Rock! Child Care Center Construction Update

Title

Kids Rock! Child Care Center Construction Update

Body

Construction is remaining on schedule. The following work has been completed:

Tiling

Painting

Interior and exterior signage

Majority of mechanical, electrical, low voltage, and plumbing scopes

Mounting lighting control boxes in Mechanical room

Floor prep throughout

Installation of Division 10 items (toilet accessories, grab bars, mirrors, AED Cabinets, Fire extinguisher cabinets, corner guards, etc.)

Pocket door frame

Rough Kitchen cleaning

 

The following work is scheduled to be completed this month:

Continue w/ LVT Flooring

Carpet

Hang door slabs and hardware

Continue electrical finishes

Control panels & H lighting in loading dock/storage

Hood and walk-in cooler startup

Install eye wash station

Mechanical room labeling and relocate heater in loading dock

Program boiler #2

 

Punch list items will be discussed toward the end of the month.  Appliances and FF&E are scheduled to start being delivered the week of Feb 3, 2025. 

 

Kids Rock! has hired Sara Robinson as the Executive Director.  Kids Rock! is accepting applications for Assistant Director, Food Service Manager, Lead Teacher and Aide positions.