Construction activities completed in October:

•                     The new roof top units were installed

•                     Other roof penetrations completed

•                     MEP above ceilings

•                     Low voltage rough ins

•                     Painting

•                     Ceiling grid

•                     Ceramic tiling

•                     Casework delivery & install began

•                     Ceiling mounted fixtures began

•                     Landscaping finished

•                     Aluminum storefronts finished

•                     Kitchen hood and Ansul system

•                     FRP in kitchen

•                     Flooring in kitchen

•                     Bathroom fixtures began

•                     Mechanical room scopes

 

Construction activities planned for November:

•                     Finish Casework install

•                     Solid surfacing

•                     Continue plumbing fixtures

•                     Continue ceiling mounted fixtures

•                     Low voltage, security & alarms

•                     Wall protection

•                     Resilient athletic flooring in activity room

•                     Kitchen equipment

•                     Coiling & overhead door

•                     Specialty ceilings

•                     Toilet compartments

•                     Toilet accessories

•                     Sealed concrete floors