Legislation Details

File #: 2024-283    Version: 1
Type: Motion Status: Passed
File created: 10/3/2024 In control: City Council
On agenda: 10/8/2024 Final action: 10/8/2024
Title: Contract Change Orders No. 8 and 9 for a Net Decrease of $7,040 to Knutson Construction RE: Childcare Facility.
Attachments: 1. PCI #12-#15 Misc Scope Changes 9.24.2024 with isg signature, 2. PCI #016 - PR#6 Drawing Revisions 9.24.2024 with isg signature

title

Contract Change Orders No. 8 and 9 for a Net Decrease of $7,040 to Knutson Construction RE: Childcare Facility.

 

body

Change order no. 8 includes a variety of miscellaneous credits and one addition to the scope of work. The credits come from omitting the back flow preventer, omitting transfer ducts in certain rooms, and removing ADA concrete signage.  Additional metal fabrications were needed for the added roof penetration duct framework for kitchen equipment. This results in a net increase of $1,150. Change order no. 9 is for a credit due to omitting fencing on the northeast side of the property.  This results in a net decrease of $8,190. The GMP remains unchanged at $7,228,835 and contingency balance remains strong at $231,788.75 after these changes.

 

recommendation

City Administrator Recommendation: City Council Approve Contract Change Orders No. 8 and 9 for a Net Decrease of $8,190 to Knutson Construction RE: Childcare Facility.