Progress continues on the childcare center construction project. As construction activities are taking place, schedules are reviewed in our OAC meetings on a weekly basis for input and adjustments.To date, there have been zero reported injuries on the job site. Drywall assemblies are about 80% finished and are expected to be completed around 9/13/24. Painting is starting and should be complete by the end of the month. Tiling and ceilings will start toward the end of the month. Casework and flooring are expected to follow in October. About 50% of the exterior improvements are complete (curbing and concrete) and the rest (asphalt, landscaping, etc.) should be wrapped up before winter. The overall completion for the project is January 2025.

August scope summary:
Steel stud framing ongoing - only misc. scopes/areas left
-In wall backing/concealed brackets ongoing
-In wall MEP rough ins ongoing
-Above ceiling MEP rough ins ongoing
Sheet rock ongoing
-Mud & tape ongoing
-Painting started
-Walk in cooler/freezer installed
-Misc. Masonry infills ongoing
-FRP in kitchen ongoing
-Rooftop curbs complete, less condensing unit sleeper curbs
-Misc. sprinkler modifications ongoing
-Playground PIP complete, less fencing
-Exterior removals and grading complete
-Exterior aggregate complete
-Concrete curb & gutter complete
-Exterior concrete flatwork complete
-Exterior underground electrical complete

September Scope Summary:
-Finish misc. steel stud framing & gypsum assemblies
-Painting
-Ceiling Grid
-Ceiling mounted MEP fixtures
-Mass sprinkler modifications
-Ceramic tiling in restrooms
-Casework towards the end of the month
-Roof hatch/ships ladder & roof anchors
-RTU/MAU delivery and install
-Overhead door removal and install / Insulated metal panel install
-Rooftop condensing units for walk ins
-Stainless steel & kitchen hood
-Fencing
-Asphalt
-Landscaping
-Natural gas (CenterPoint)

Kids Rock! has officially hired Dina Brown...