Legislation Details

File #: 2024-215    Version: 1
Type: Motion Status: Passed
File created: 7/18/2024 In control: City Council
On agenda: 7/23/2024 Final action: 7/23/2024
Title: Application and Certification for Payment No. 3 for $557,011.12 to Knutson Construction RE: Childcare Facility.
Attachments: 1. 26330 Luverne Renovation Pay Application 03 - 2024-07-09

title

Application and Certification for Payment No. 3 for $557,011.12 to Knutson Construction RE: Childcare Facility.

 

body

This payment application includes continued miscellaneous demolition throughout the childcare building and demolition of exterior metal panels for structural steel access. Mechanical and electrical contractors continued with their above ceiling rough in and plumbers finished the underground plumbing. Following inspections, contractors prepped for concrete and installed dowels and welded wire mesh. Contractors finished concrete pour back on the interior of the building. Structural steel and steel stud framers mobilized and began their scope of work with electrical in wall rough in’s.

 

recommendation

City Administrator Recommendation: City Council Approve Application and Certification for Payment No. 3 for $557,011.12 to Knutson Construction RE: Childcare Facility.