title
Cost Proposal and Contract Change Order No. 1 for a Contract Increase of $124,088.40 for the Kids Rock! Childcare Center
body
This proposal request functions as a change order for the Childcare Center renovation project. The majority of this change order addresses unforeseen conditions discovered within the existing building. These include the need for door hardware, removal and replacement of clay tile and gypsum board insulation and vapor barriers in specific areas. Additionally, structural reinforcement dowls under the slab on grade are required to meet current building codes. The requested changes will be funded from the project's contingency reserve, which will be $235,912 after this change order.
recommendation
City Administrator Recommendation: City Council Approve Cost Proposal and Contract Change Order No. 1 for a Contract Increase of $124,088.40 for the Kids Rock! Childcare Center.